Given EVM data, estimate the cost at completion of a projectusing the method “EAC based on combined

Given EVM data, estimate the cost at completion of a projectusing the method “EAC based on combined

Given EVM data, estimate the cost at completion of a projectusing the method “EAC based on combined cost and scheduleperformance.”BCWS = $82.2MBCWP = $70.5MACWP = $95.5MBAC = $105.5MA) $130MB) $150MC) $160MD) $170M